Sunday, November 22, 2015

November 2015 updated

Here is photos for rafflesia November 2015 updated. The block a already construct to 20 floors. The block B to 22floors.

Tuesday, August 4, 2015

Sunday, August 2, 2015

August 2015 updated.

Go to visit Rafflesia condo this sunday. 1st August 2015. The construction already reach 16 floors. The swimming pool at lever 7 already can see the pool shape.  It look progress smoothly.

Wednesday, July 8, 2015

Rafflesia condo July update.

Visit the side , it up to 15 floors already. Look progress smoothly. The swimming pool also start to built.

Sunday, May 24, 2015

Rafflesia May 2015 update

Go to the rafflesia Contruction side this saturday. The construction already up to 12floors. Around two floors one month.

Sunday, May 3, 2015